Projects/Space2.0: Difference between revisions
< Projects
No edit summary |
|||
Line 14: | Line 14: | ||
* Behangen cq. verven van de overige muren | * <b>Behangen cq. verven van de overige muren</b> | ||
** Depends: none | ** Depends: none | ||
** Deadline: 23 okt | ** Deadline: 23 okt | ||
** Contact: polyfloyd | ** Contact: polyfloyd | ||
* Opruimen opslag verhuurder | * <b>Opruimen opslag verhuurder</b> | ||
** Depends: verhuurder | ** Depends: verhuurder | ||
** Deadline: 29 okt | ** Deadline: 29 okt | ||
** Contact: Jeroen | ** Contact: Jeroen | ||
* Floorplan | * <b>Floorplan</b> | ||
** Depends: none | ** Depends: none | ||
** Deadline: 1 nov | ** Deadline: 1 nov | ||
** Contact: AK | ** Contact: AK | ||
* Water aan/afvoer chemiehoek | * <b>Water aan/afvoer chemiehoek</b> | ||
** Depends: floorplan | ** Depends: floorplan | ||
** Deadline: 9 nov | ** Deadline: 9 nov | ||
** Contact: eightdot | ** Contact: eightdot | ||
* Wanden | * <b>Wanden</b> | ||
** Depends: Water aan/afvoer chemiehoek | ** Depends: Water aan/afvoer chemiehoek | ||
** Deadline: 13 nov | ** Deadline: 13 nov | ||
** Contact: hobbybob | ** Contact: hobbybob | ||
* Deuren | * <b>Deuren</b> | ||
** Depends: none | ** Depends: none | ||
** Deadline: 13 nov | ** Deadline: 13 nov | ||
** Contact: hobbybob | ** Contact: hobbybob | ||
* Laminaat leggen/vloer | * <b>Laminaat leggen/vloer</b> | ||
** Depends: Behangen cq. verven van de overige muren | ** Depends: Behangen cq. verven van de overige muren | ||
** Depends: Wanden (wat betekend dat laminaat tot aan de nieuwe wanden gelegd kan worden) | ** Depends: Wanden (wat betekend dat laminaat tot aan de nieuwe wanden gelegd kan worden) | ||
Line 51: | Line 51: | ||
** Contact: hobbybob | ** Contact: hobbybob | ||
* Behangen cq. verven muur met de deuren | * <b>Behangen cq. verven muur met de deuren</b> | ||
** Depends: deuren | ** Depends: deuren | ||
** Deadline: 15 nov | ** Deadline: 15 nov | ||
** Contact: polyfloyd | ** Contact: polyfloyd | ||
* Elektra in de space | * <b>Elektra in de space</b> | ||
** Depends: floorplan | ** Depends: floorplan | ||
** Deadline: 1 dec | ** Deadline: 1 dec | ||
** Contact: AK? | ** Contact: AK? | ||
* Verlichting | * <b>Verlichting</b> | ||
** Depends: elektra | ** Depends: elektra | ||
** Deadline: 1 dec? | ** Deadline: 1 dec? | ||
** Contact: polyfloyd | ** Contact: polyfloyd | ||
* Netwerkkabels | * <b>Netwerkkabels</b> | ||
** Depends: floorplan | ** Depends: floorplan | ||
** Depends: serverhok | ** Depends: serverhok | ||
Line 72: | Line 72: | ||
** Contact: AK | ** Contact: AK | ||
* Internet | * <b>Internet</b> | ||
** Depends: levering door ISP | ** Depends: levering door ISP | ||
** Depends: elektra | ** Depends: elektra | ||
Line 80: | Line 80: | ||
** Contact: AK & Wilco | ** Contact: AK & Wilco | ||
* Verven radiator makerhoek | * <b>Verven radiator makerhoek</b> | ||
** Depends: none | ** Depends: none | ||
** Deadline: 10/11 dec | ** Deadline: 10/11 dec | ||
** Contact: polyfloyd | ** Contact: polyfloyd | ||
* Meubilair (tafels + stoelen) | * <b>Meubilair (tafels + stoelen)</b> | ||
** Depends: laminaat | ** Depends: laminaat | ||
** Depends: floorplan | ** Depends: floorplan | ||
Line 91: | Line 91: | ||
** Contact: AK | ** Contact: AK | ||
* Opslag cq. racken | * <b>Opslag cq. racken</b> | ||
** Depends: wanden | ** Depends: wanden | ||
** Depends: deuren | ** Depends: deuren | ||
Line 97: | Line 97: | ||
** Contact: hobbybob | ** Contact: hobbybob | ||
* Serverhok | * <b>Serverhok</b> | ||
** Depends: wanden | ** Depends: wanden | ||
** Depends: elektra | ** Depends: elektra | ||
Line 103: | Line 103: | ||
** Contact: AK | ** Contact: AK | ||
* Bescherming van het laminaat | * <b>Bescherming van het laminaat</b> | ||
** Depends: none | ** Depends: none | ||
** Deadline: 10/11 dec | ** Deadline: 10/11 dec | ||
** Contact: Jeroen | ** Contact: Jeroen | ||
* Draadloze deurbel | * <b>Draadloze deurbel</b> | ||
** Depends: elektra | ** Depends: elektra | ||
** Deadline: 10/11 dec | ** Deadline: 10/11 dec | ||
** Contact: Kartoffel | ** Contact: Kartoffel | ||
* Alarmsysteem | * <b>Alarmsysteem</b> | ||
** Depends: internet | ** Depends: internet | ||
** Depends: elektra | ** Depends: elektra | ||
Line 119: | Line 119: | ||
** Contact: Jeroen & Wilco | ** Contact: Jeroen & Wilco | ||
* Glasvezelbehang houthok | * <b>Glasvezelbehang houthok</b> | ||
** Depends: wanden | ** Depends: wanden | ||
** Deadline: 31 dec? | ** Deadline: 31 dec? | ||
** Contact: polyfloyd | ** Contact: polyfloyd | ||
* | * <b>Deurropeners cq. doorsystem</b> | ||
** Depends: elektra | ** Depends: elektra | ||
** Deadline: 15 jan (gefasseerd: eerst bovendeur, later buitendeur na verhuizing) | ** Deadline: 15 jan (gefasseerd: eerst bovendeur, later buitendeur na verhuizing) | ||
** Contact: Wilco & bob & eightdot? | ** Contact: Wilco & bob & eightdot? | ||
* Werkbank makerhoek | * <b>Werkbank makerhoek</b> | ||
** Depends: laminaat | ** Depends: laminaat | ||
** Depends: verven radiator makerhoek | ** Depends: verven radiator makerhoek | ||
Line 135: | Line 135: | ||
** Contact: mro | ** Contact: mro | ||
* Werkbank houthok | * <b>Werkbank houthok</b> | ||
** Depends: wanden | ** Depends: wanden | ||
** Depends: laminaat | ** Depends: laminaat | ||
Line 141: | Line 141: | ||
** Contact: mro | ** Contact: mro | ||
* Keukenblok | * <b>Keukenblok</b> | ||
** Depends: laminaat | ** Depends: laminaat | ||
** Depends: deuren | ** Depends: deuren | ||
Line 147: | Line 147: | ||
** Contact: mro | ** Contact: mro | ||
* Zekering automaat aanpassen</b> | * <b>Zekering automaat aanpassen</b> | ||
** Depends: none | ** Depends: none | ||
** Deadline: 31 jan? | ** Deadline: 31 jan? | ||
** Contact: eightdot | ** Contact: eightdot | ||
== Kluslog == | == Kluslog == |
Revision as of 21:42, 23 October 2016
Project Space 2.0 | |
---|---|
Name | Space 2.0 |
Start | 2016/10/17 |
End | |
Contact | Hobbybob, AK47, Vuurtorenjeroen, mro, eightdot, Maeddoc, you?! |
Website | https://bitlair.nl |
Information | Nieuwe ruimte |
Status | Alpha |
Zie ook Projects/Verhuizen
Activiteiten & afhankelijkheden
Bij afronding strikethrough gebruiken!
- Behangen cq. verven van de overige muren
- Depends: none
- Deadline: 23 okt
- Contact: polyfloyd
- Opruimen opslag verhuurder
- Depends: verhuurder
- Deadline: 29 okt
- Contact: Jeroen
- Floorplan
- Depends: none
- Deadline: 1 nov
- Contact: AK
- Water aan/afvoer chemiehoek
- Depends: floorplan
- Deadline: 9 nov
- Contact: eightdot
- Wanden
- Depends: Water aan/afvoer chemiehoek
- Deadline: 13 nov
- Contact: hobbybob
- Deuren
- Depends: none
- Deadline: 13 nov
- Contact: hobbybob
- Laminaat leggen/vloer
- Depends: Behangen cq. verven van de overige muren
- Depends: Wanden (wat betekend dat laminaat tot aan de nieuwe wanden gelegd kan worden)
- Depends: deur naar houthok
- Deadline: 15 nov
- Contact: hobbybob
- Behangen cq. verven muur met de deuren
- Depends: deuren
- Deadline: 15 nov
- Contact: polyfloyd
- Elektra in de space
- Depends: floorplan
- Deadline: 1 dec
- Contact: AK?
- Verlichting
- Depends: elektra
- Deadline: 1 dec?
- Contact: polyfloyd
- Netwerkkabels
- Depends: floorplan
- Depends: serverhok
- Deadline: 10/11 dec
- Contact: AK
- Internet
- Depends: levering door ISP
- Depends: elektra
- Depends: serverhok
- Depends: bekabeling woonhuis
- Deadline: 10/11 dec
- Contact: AK & Wilco
- Verven radiator makerhoek
- Depends: none
- Deadline: 10/11 dec
- Contact: polyfloyd
- Meubilair (tafels + stoelen)
- Depends: laminaat
- Depends: floorplan
- Deadline: 10/11 dec
- Contact: AK
- Opslag cq. racken
- Depends: wanden
- Depends: deuren
- Deadline: 10/11 dec
- Contact: hobbybob
- Serverhok
- Depends: wanden
- Depends: elektra
- Deadline: 10/11 dec
- Contact: AK
- Bescherming van het laminaat
- Depends: none
- Deadline: 10/11 dec
- Contact: Jeroen
- Draadloze deurbel
- Depends: elektra
- Deadline: 10/11 dec
- Contact: Kartoffel
- Alarmsysteem
- Depends: internet
- Depends: elektra
- Deadline: 31 dec?
- Contact: Jeroen & Wilco
- Glasvezelbehang houthok
- Depends: wanden
- Deadline: 31 dec?
- Contact: polyfloyd
- Deurropeners cq. doorsystem
- Depends: elektra
- Deadline: 15 jan (gefasseerd: eerst bovendeur, later buitendeur na verhuizing)
- Contact: Wilco & bob & eightdot?
- Werkbank makerhoek
- Depends: laminaat
- Depends: verven radiator makerhoek
- Deadline: 31 jan?
- Contact: mro
- Werkbank houthok
- Depends: wanden
- Depends: laminaat
- Deadline: 31 jan?
- Contact: mro
- Keukenblok
- Depends: laminaat
- Depends: deuren
- Deadline: 31 jan?
- Contact: mro
- Zekering automaat aanpassen
- Depends: none
- Deadline: 31 jan?
- Contact: eightdot
Kluslog
17-10-2016
- Sleutel nieuwe pand in ontvangst genomen
19-10-2016
- Ruimte opgemeten om in kaart te brengen
- Parket & ondervloer gehaald
20-10-2016
- Raamkozijnen geschuurd
- Bouwmarkt bezocht, veel klusmateriaal gekocht
21-10-2016
- Schoonmaken
- Muren behangen
- Raamkozijnen lakken
- Events/2016-10-21_Klusdag_1_Space_2.0
22-10-2016
- Gipswanden behangklaar maken
- Schoonmaken
- Gipswanden behangen en afwerken
- Schilderen
- Events/2016-10-22_Klusdag_2
23-10-2016
- Gipswanden behangklaar maken
- Schoonmaken
- Gipswanden behangen en afwerken
- Schilderen
- Events/2016-10-23_Klusdag_3
26-10-2016
- Nieuwe gipswanden naar boven brengen
29-10-2016
- Verhuurder helpen met opruimen/leegruimen opslag
Plattegrond (PDF)
https://bitlair.nl/images/e/ec/Plattegrond_Space_2.0_1OP10.pdf