The outer shell is finished, x axis and y-axis are moving, air hose and wires support on x-axis follow the cart. | The outer shell is finished, x axis and y-axis are moving, air hose and wires support on x-axis follow the cart. | ||
water cooling fan's mounted | water cooling fan's mounted | ||
== Current ideas/changes:== | == Current ideas/changes:== | ||
Line 8: | Line 7: | ||
== Next priorities:== | == Next priorities:== | ||
* Order air flow ==> (mro) | * Order air flow ==> (mro) | ||
* Order Bed frame and support rods ==> hobbybob upload pics | * Order Bed frame and support rods ==> hobbybob upload pics | ||
* Order acrilyc for cover-lid (disformes at 10600nm light) | * Order acrilyc for cover-lid (disformes at 10600nm light) | ||
Line 17: | Line 15: | ||
* power distribution to high voltage transformer | * power distribution to high voltage transformer | ||
* power distribution to water cooling | * power distribution to water cooling | ||
* duration time meter | |||
* emergency stop | |||
* key switch | |||
== Nice to haves for now:== | == Nice to haves for now:== | ||
* Z-bed | * Z-bed | ||
** manual | |||
** electric | |||
* Water temperature in and out sensors | * Water temperature in and out sensors | ||
== Design changes for next cutters == | == Design changes for next cutters == |
Latest revision as of 21:15, 2 June 2013
The outer shell is finished, x axis and y-axis are moving, air hose and wires support on x-axis follow the cart. water cooling fan's mounted
Current ideas/changes:
- we move from the idea of honeycomb to laminar airflow system with parallel rods to support the materials.
Next priorities:
- Order air flow ==> (mro)
- Order Bed frame and support rods ==> hobbybob upload pics
- Order acrilyc for cover-lid (disformes at 10600nm light)
- Order Hose connectors for water cooling
- Order magnetic switch for top-cover
- power cord connector in outer shell
- power distribution to air assist pump
- power distribution to high voltage transformer
- power distribution to water cooling
- duration time meter
- emergency stop
- key switch
Nice to haves for now:
- Z-bed
- manual
- electric
- Water temperature in and out sensors
Design changes for next cutters
- outershell front remove left airhole (in beam path when mirror fails)
- outershell front remove right airhole (copy/paste bug)
- outershell front top right cover corner needs to move by 1 cm.
- outershell top engine bay cover, create holes for hinges
Done:
- Inner frame created
- Laser tubes ordered and arrived
- Optics Ordered:
- mirors
- lenses
- glasses