Projects/Space2.0: Difference between revisions

From Hackerspace Amersfoort
Jump to navigation Jump to search
No edit summary
Line 14: Line 14:




* Behangen cq. verven van de overige muren
* <b>Behangen cq. verven van de overige muren</b>
** Depends: none
** Depends: none
** Deadline: 23 okt
** Deadline: 23 okt
** Contact: polyfloyd
** Contact: polyfloyd


* Opruimen opslag verhuurder
* <b>Opruimen opslag verhuurder</b>
** Depends: verhuurder
** Depends: verhuurder
** Deadline: 29 okt
** Deadline: 29 okt
** Contact: Jeroen
** Contact: Jeroen
   
   
* Floorplan
* <b>Floorplan</b>
** Depends: none
** Depends: none
** Deadline: 1 nov
** Deadline: 1 nov
** Contact: AK
** Contact: AK


* Water aan/afvoer chemiehoek
* <b>Water aan/afvoer chemiehoek</b>
** Depends: floorplan
** Depends: floorplan
** Deadline: 9 nov
** Deadline: 9 nov
** Contact: eightdot
** Contact: eightdot
   
   
* Wanden
* <b>Wanden</b>
** Depends: Water aan/afvoer chemiehoek  
** Depends: Water aan/afvoer chemiehoek  
** Deadline: 13 nov
** Deadline: 13 nov
** Contact: hobbybob
** Contact: hobbybob
   
   
* Deuren
* <b>Deuren</b>
** Depends: none
** Depends: none
** Deadline: 13 nov
** Deadline: 13 nov
** Contact: hobbybob
** Contact: hobbybob
   
   
* Laminaat leggen/vloer
* <b>Laminaat leggen/vloer</b>
** Depends: Behangen cq. verven van de overige muren
** Depends: Behangen cq. verven van de overige muren
** Depends: Wanden (wat betekend dat laminaat tot aan de nieuwe wanden gelegd kan worden)
** Depends: Wanden (wat betekend dat laminaat tot aan de nieuwe wanden gelegd kan worden)
Line 51: Line 51:
** Contact: hobbybob
** Contact: hobbybob
   
   
* Behangen cq. verven muur met de deuren
* <b>Behangen cq. verven muur met de deuren</b>
** Depends: deuren
** Depends: deuren
** Deadline: 15 nov
** Deadline: 15 nov
** Contact: polyfloyd
** Contact: polyfloyd
   
   
* Elektra in de space
* <b>Elektra in de space</b>
** Depends: floorplan
** Depends: floorplan
** Deadline: 1 dec
** Deadline: 1 dec
** Contact: AK?
** Contact: AK?


* Verlichting
* <b>Verlichting</b>
** Depends: elektra
** Depends: elektra
** Deadline: 1 dec?
** Deadline: 1 dec?
** Contact: polyfloyd
** Contact: polyfloyd
   
   
* Netwerkkabels
* <b>Netwerkkabels</b>
** Depends: floorplan
** Depends: floorplan
** Depends: serverhok
** Depends: serverhok
Line 72: Line 72:
** Contact: AK
** Contact: AK
   
   
* Internet
* <b>Internet</b>
** Depends: levering door ISP
** Depends: levering door ISP
** Depends: elektra
** Depends: elektra
Line 80: Line 80:
** Contact: AK & Wilco
** Contact: AK & Wilco
   
   
* Verven radiator makerhoek
* <b>Verven radiator makerhoek</b>
** Depends: none
** Depends: none
** Deadline: 10/11 dec
** Deadline: 10/11 dec
** Contact: polyfloyd
** Contact: polyfloyd


* Meubilair (tafels + stoelen)
* <b>Meubilair (tafels + stoelen)</b>
** Depends: laminaat
** Depends: laminaat
** Depends: floorplan
** Depends: floorplan
Line 91: Line 91:
** Contact: AK
** Contact: AK


* Opslag cq. racken
* <b>Opslag cq. racken</b>
** Depends: wanden
** Depends: wanden
** Depends: deuren
** Depends: deuren
Line 97: Line 97:
** Contact: hobbybob
** Contact: hobbybob


* Serverhok
* <b>Serverhok</b>
** Depends: wanden
** Depends: wanden
** Depends: elektra
** Depends: elektra
Line 103: Line 103:
** Contact: AK
** Contact: AK


* Bescherming van het laminaat
* <b>Bescherming van het laminaat</b>
** Depends: none
** Depends: none
** Deadline: 10/11 dec
** Deadline: 10/11 dec
** Contact: Jeroen
** Contact: Jeroen


* Draadloze deurbel
* <b>Draadloze deurbel</b>
** Depends: elektra
** Depends: elektra
** Deadline: 10/11 dec
** Deadline: 10/11 dec
** Contact: Kartoffel
** Contact: Kartoffel


* Alarmsysteem
* <b>Alarmsysteem</b>
** Depends: internet
** Depends: internet
** Depends: elektra
** Depends: elektra
Line 119: Line 119:
** Contact: Jeroen & Wilco
** Contact: Jeroen & Wilco


* Glasvezelbehang houthok
* <b>Glasvezelbehang houthok</b>
** Depends: wanden
** Depends: wanden
** Deadline: 31 dec?
** Deadline: 31 dec?
** Contact: polyfloyd
** Contact: polyfloyd


* Duuropeners cq. doorsystem
* <b>Deurropeners cq. doorsystem</b>
** Depends: elektra
** Depends: elektra
** Deadline: 15 jan (gefasseerd: eerst bovendeur, later buitendeur na verhuizing)
** Deadline: 15 jan (gefasseerd: eerst bovendeur, later buitendeur na verhuizing)
** Contact: Wilco & bob & eightdot?
** Contact: Wilco & bob & eightdot?


* Werkbank makerhoek
* <b>Werkbank makerhoek</b>
** Depends: laminaat
** Depends: laminaat
** Depends: verven radiator makerhoek
** Depends: verven radiator makerhoek
Line 135: Line 135:
** Contact: mro
** Contact: mro
   
   
* Werkbank houthok
* <b>Werkbank houthok</b>
** Depends: wanden
** Depends: wanden
** Depends: laminaat
** Depends: laminaat
Line 141: Line 141:
** Contact: mro
** Contact: mro
   
   
* Keukenblok
* <b>Keukenblok</b>
** Depends: laminaat
** Depends: laminaat
** Depends: deuren
** Depends: deuren
Line 147: Line 147:
** Contact: mro
** Contact: mro
   
   
* Zekering automaat aanpassen</b>
* <b>Zekering automaat aanpassen</b>
** Depends: none
** Depends: none
** Deadline: 31 jan?
** Deadline: 31 jan?
** Contact: eightdot
** Contact: eightdot


== Kluslog ==
== Kluslog ==

Revision as of 21:42, 23 October 2016


ArianeMax.png
Project Space 2.0
Name Space 2.0
Start 2016/10/17
End
Contact Hobbybob, AK47, Vuurtorenjeroen, mro, eightdot, Maeddoc, you?!
Website https://bitlair.nl
Information Nieuwe ruimte
Status Alpha


Zie ook Projects/Verhuizen

Activiteiten & afhankelijkheden

Bij afronding strikethrough gebruiken!


  • Behangen cq. verven van de overige muren
    • Depends: none
    • Deadline: 23 okt
    • Contact: polyfloyd
  • Opruimen opslag verhuurder
    • Depends: verhuurder
    • Deadline: 29 okt
    • Contact: Jeroen
  • Floorplan
    • Depends: none
    • Deadline: 1 nov
    • Contact: AK
  • Water aan/afvoer chemiehoek
    • Depends: floorplan
    • Deadline: 9 nov
    • Contact: eightdot
  • Wanden
    • Depends: Water aan/afvoer chemiehoek
    • Deadline: 13 nov
    • Contact: hobbybob
  • Deuren
    • Depends: none
    • Deadline: 13 nov
    • Contact: hobbybob
  • Laminaat leggen/vloer
    • Depends: Behangen cq. verven van de overige muren
    • Depends: Wanden (wat betekend dat laminaat tot aan de nieuwe wanden gelegd kan worden)
    • Depends: deur naar houthok
    • Deadline: 15 nov
    • Contact: hobbybob
  • Behangen cq. verven muur met de deuren
    • Depends: deuren
    • Deadline: 15 nov
    • Contact: polyfloyd
  • Elektra in de space
    • Depends: floorplan
    • Deadline: 1 dec
    • Contact: AK?
  • Verlichting
    • Depends: elektra
    • Deadline: 1 dec?
    • Contact: polyfloyd
  • Netwerkkabels
    • Depends: floorplan
    • Depends: serverhok
    • Deadline: 10/11 dec
    • Contact: AK
  • Internet
    • Depends: levering door ISP
    • Depends: elektra
    • Depends: serverhok
    • Depends: bekabeling woonhuis
    • Deadline: 10/11 dec
    • Contact: AK & Wilco
  • Verven radiator makerhoek
    • Depends: none
    • Deadline: 10/11 dec
    • Contact: polyfloyd
  • Meubilair (tafels + stoelen)
    • Depends: laminaat
    • Depends: floorplan
    • Deadline: 10/11 dec
    • Contact: AK
  • Opslag cq. racken
    • Depends: wanden
    • Depends: deuren
    • Deadline: 10/11 dec
    • Contact: hobbybob
  • Serverhok
    • Depends: wanden
    • Depends: elektra
    • Deadline: 10/11 dec
    • Contact: AK
  • Bescherming van het laminaat
    • Depends: none
    • Deadline: 10/11 dec
    • Contact: Jeroen
  • Draadloze deurbel
    • Depends: elektra
    • Deadline: 10/11 dec
    • Contact: Kartoffel
  • Alarmsysteem
    • Depends: internet
    • Depends: elektra
    • Deadline: 31 dec?
    • Contact: Jeroen & Wilco
  • Glasvezelbehang houthok
    • Depends: wanden
    • Deadline: 31 dec?
    • Contact: polyfloyd
  • Deurropeners cq. doorsystem
    • Depends: elektra
    • Deadline: 15 jan (gefasseerd: eerst bovendeur, later buitendeur na verhuizing)
    • Contact: Wilco & bob & eightdot?
  • Werkbank makerhoek
    • Depends: laminaat
    • Depends: verven radiator makerhoek
    • Deadline: 31 jan?
    • Contact: mro
  • Werkbank houthok
    • Depends: wanden
    • Depends: laminaat
    • Deadline: 31 jan?
    • Contact: mro
  • Keukenblok
    • Depends: laminaat
    • Depends: deuren
    • Deadline: 31 jan?
    • Contact: mro
  • Zekering automaat aanpassen
    • Depends: none
    • Deadline: 31 jan?
    • Contact: eightdot

Kluslog

17-10-2016

  • Sleutel nieuwe pand in ontvangst genomen

19-10-2016

  • Ruimte opgemeten om in kaart te brengen
  • Parket & ondervloer gehaald

20-10-2016

  • Raamkozijnen geschuurd
  • Bouwmarkt bezocht, veel klusmateriaal gekocht

21-10-2016

22-10-2016

23-10-2016

26-10-2016

  • Nieuwe gipswanden naar boven brengen

29-10-2016

  • Verhuurder helpen met opruimen/leegruimen opslag


Plattegrond (PDF)

https://bitlair.nl/images/e/ec/Plattegrond_Space_2.0_1OP10.pdf

Foto's